Niseko Town Landscape Ordinance
Heisei 14
season | Implementation content | Issues to consider | Schedule | ||
December | Middle | The 1st Office Project Team | ·confirmation of the schedule · How to make consistency with various plans in the town | 12月13日 | |
Late | The 2nd Office Project Team | · About the content included in the ordinance (free discussion) | December 26 | ||
January | Early | - | - | - | |
Middle | - | - | - | ||
Late | - | - | - | ||
February | Early | The 3rd Office Project Team | · About the content included in the ordinance (confirmation) · About the system of ordinance | February 5 | |
Middle | - | - | - | ||
Late | The 4th Office Project Team | · Regulations on land development and outdoor advertising materials | 2月28日 | ||
In March | Early | - | - | - | |
Middle | The 5th Office Project Team | · Regulations on land development and outdoor advertising materials | 3月18日 | ||
Late | - | - | - |
Heisei er 2003
season | Implementation content | Issues to consider | Schedule | ||
April | Early | - | - | - | |
Middle | - | - | - | ||
Late | - | - | - | ||
May | Early | - | - | - | |
Middle | The 6th Office Project Team | · About the Ordinance Proposal (Tatamidai) · Regulations on land development and outdoor advertising materials · About the subsidy system | 5月14日 | ||
Late | - | - | - | ||
June | Early | Town development committee | · About the Ordinance Proposal (Tatamidai) | 6月3日 | |
Middle | Environmental Council | · About the Ordinance Proposal (Tatamidai) | 6月10日 | ||
Late | Inhabitants review meeting | · About the Ordinance Proposal (Tatamidai) | 6月24日 | ||
July | Early | Correction work based on opinion etc. issued by the above committee etc. | - | - | |
Middle | |||||
Late | |||||
August | Early | Consultation with Hokkaido | · About regulation of outdoor advertisement · About restrictions when developing land etc. | Late October | |
Middle | Presented at the Sapporo Local Autonomy Law Study Group, heard opinions | · About the Ordinance Proposal (Tatamidai) | 8月21日 | ||
Late | - | - | - | ||
September | Early | - | - | - | |
Middle | - | - | - | ||
Late | - | - | - | ||
October | Early | - | - | - | |
Middle | - | - | - | ||
Late | - | - | - | ||
November | Early | Revision work after receiving the consultation etc. (Hokkaido · Sapporo Local Autonomy Law Study Group) | - | - | |
Middle | |||||
Late | Publication of ordinance proposal, public opinion recruitment | · About the ordinance draft (draft) | - | ||
December | Early | The 7th Office Project Team | · About the ordinance draft (draft) | - | |
Middle | Town development committee | · About the ordinance draft (draft) | - | ||
Late | - | - | - | ||
January | Early | - | - | - | |
Middle | - | - | - | ||
Late | Confirmation of draft ordinance (final) | · Explanation to town council member | - | ||
February | Early | Inspection of the draft ordinance started | - | - | |
Middle | - | - | - | ||
Late | - | - | - | ||
In March | Early | Congress submission | - | - | |
Middle | - | - | - | ||
Late | - | - | - |
Inquiries regarding information on this page
- City Construction Division City Planning Section
- TEL:0136-44-2121
- FAX:0136-44-3500