final design

The 172th town planning lecture "About the policies of the new government building implementation design" will be held!

The new building construction basic design was completed on March 20, 1940, but there was still a problem of "reducing the area" in order to reduce the construction cost.
On April 18, we concluded a contract with the Atelier Bank Co., Ltd., which carried out the basic design work, "Outsourcing Contract for New Government Building Construction Design", and discussed the issue of "Reducing the area" at the New Government Building Construction Review Committee and the Working Group It was.
In this townspeaker lecture, we will explain the explanation of the basic design reduced to "3700 square meters → 3300 square meters" while maintaining and developing the basic design function, and the policy of future implementation design.
Please come by all means.
Date and timeJuly 17 (Tue) 18: 30 - 20: 00
VenueNiseko Town citizens center second floor training room 1
Application methodNo advance application required, please come directly to the venue
Inquiries総務課庁舎整備係(黒瀧・北野・田中)0136-44-2121

172 times town planning townsmen course "Niseko Town was held for the new building construction carried out the design of the policy"!

At the 172nd Town Development Townsman Lecture held on July 17, "1. History of new government building maintenance", "2. Goals/policy of new government building maintenance", "3. Reexamination of basic design (area We explained to the participants about "Reduction of the number"), "4. Future schedule", and "5. Relationship with Landscape Ordinance". We would like to introduce the contents and questions that we received.
1. History of New Government Building Development
Regarding maintenance of the New Government Office, we have done quite a lot of meetings through the townspeople lectures, the council of parliaments and the in-service meeting. And we have summarized as many opinions and requests as we have made remarks at these meetings whenever possible.
a
2. Goals and policies of new Government building improvement
I reconfirmed the concept of the new government building and explained the flow of the implementation design in the future. In the future, we plan to review construction design, work environment examination, structure study, facility consideration, energy saving consideration by December, accumulate building costs by February, and apply building confirmation application in March.
3. Review of basic design (reduction of area)
After completing the basic design, it was necessary to reduce the area and reduce the construction cost. For that reason, we reviewed the development and maintenance of the office function while reducing the area at various meetings. I explained what kind of drawing it was as a result of examination here.
 
4. Future schedule
I explained the whole schedule of the future and the detailed schedule of FY2030.
5.Explanation based on the Landscape Ordinance
Since the new government building corresponds to a new construction of a building with a height of 10 meters and a total area of more than 1,000 square meters, we explained what the new government building looks like from the surroundings based on the Landscape Ordinance.
6. Questions, etc.
Q1 Why did you quit the stairwell in the government building?
Since I aimed at A1 ZEB Ready, I judged it better to quit the colonnade.
 
Q2 Is not the feeling of liberation deprived by the fact that there is no longer a blow-by?
A2 We plan to take natural light on the floor of the first floor, the floor, the height and the height. By this we feel that opening feeling will come out.
 
Q3 What is there like a fence on the rooftop? Also please tell me the reason why the left and right heights are different.
A3 It is a fence for preventing snow cover. I set the east side where snow covers are easy to make high.
 
Q4 I think that it will become a government building where it is easier for a curved line, such as a roof around, to enter.
A4 We will consider whether it is possible or not considering issues such as preventing snow cover.
 